CIPAA Adjudicator Jurisdiction in Malaysia: Key Insights for Construction Dispute Resolution

BY CIPAA ADVISORS


CIPAA lawyer in Malaysia reviewing construction payment dispute for adjudication process

CIPAA Adjudicator Jurisdiction in Malaysia: Key Insights for Construction Dispute Resolution


Introduction to CIPAA 2012 and Jurisdictional Limits


The Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) is a vital tool in resolving construction payment disputes in Malaysia. It provides a fast-track mechanism for contractors, subcontractors, and consultants to recover unpaid claims. However, one often overlooked aspect is the jurisdiction of the adjudicator.


Recent case law highlights the serious implications when an adjudicator exceeds their jurisdiction by considering contract clauses not raised in the CIPAA payment claim or adjudication claim. This breach can result in the entire CIPAA decision being set aside.


Why Adjudicator Jurisdiction Matters in CIPAA Claims


1. Scope of Adjudicator's Powers under CIPAA


According to Section 27(1) of CIPAA 2012, adjudicators can only decide on issues specifically raised in the payment claim, payment response, adjudication claim, and adjudication response. Any deviation—such as referencing a contractual clause not previously mentioned—can exceed their jurisdiction and potentially violate the principles of natural justice.



2. Case Law Example: Exceeding Jurisdiction is Fatal


In a landmark decision, the Federal Court of Malaysia held that an adjudicator exceeded his powers by relying on Clause 36.6 of the contract, which was not cited in the original payment claim or adjudication claim. As a result, the CIPAA adjudication decision was set aside for breaching natural justice.

❗ Key takeaway: Failure to properly plead relevant contractual clauses can render an adjudication decision invalid.

Common Mistakes in CIPAA Adjudication Malaysia


  • Failure to Cite Contractual Clauses: If your claim relies on specific contractual provisions, they must be clearly stated in the initial payment claim.


  • Raising New Issues During Adjudication: Parties should not introduce new clauses or arguments during adjudication that were not included from the outset.


  • Over-reliance on the Adjudicator’s Discretion: Adjudicators are bound by the submissions of the parties, and cannot independently introduce new contractual interpretations.


Best Practices for Filing a Successful CIPAA Claim in Malaysia


1. Engage a CIPAA Lawyer in Malaysia


A qualified CIPAA lawyer ensures your claim is prepared in compliance with the statutory requirements under CIPAA 2012. They also help identify all relevant clauses and legal issues upfront, minimizing jurisdictional risks.



2. Work with a CIPAA Consultant

A CIPAA consultant with expertise in construction contracts can assist in preparing the payment claim, identifying contractual rights, and responding to payment disputes strategically.



3. Ensure Procedural Fairness

Avoid actions that may be construed as denial of natural justice, such as surprising the other party with new arguments or clauses. Procedural fairness is fundamental to a valid adjudication decision in Malaysia.



Consequences of Breaching Adjudicator Jurisdiction


When an adjudicator oversteps their authority by introducing unauthorised clauses or arguments, the consequences can be severe:


  • Adjudication decision may be set aside under Section 15(b) of CIPAA

  • Legal costs and delays increase for both parties

  • Undermines trust in the CIPAA adjudication process


Conclusion: Jurisdiction is the Backbone of a Valid CIPAA Claim


For contractors, consultants, and employers navigating construction adjudication under CIPAA, understanding the limits of adjudicator jurisdiction is essential. Every CIPAA payment dispute in Malaysia must be carefully crafted with strict reference to the relevant contractual clauses.


By engaging experienced CIPAA lawyers and construction dispute consultants, and ensuring all relevant details are included in your initial claim, you significantly increase the likelihood of a favorable and enforceable CIPAA decision.



Need Help?


Let us help you recover your construction debt under CIPAA. Contact us today for affordable CIPAA claim services and speak to the best CIPAA claim consultants in Malaysia.


 
 
 

Comments


Financing

Allix Holdings offers in-house financing for CIPAA claims, helping construction businesses overcome financial hurdles in recovering payments.

 

Get quick access to capital, flexible terms, and expert support.

 

Apply for Claim Financing Options

CIPAA ADVISORS

Allix Holdings Sdn. Bhd.

Level 35-02 (East Wing),

Q Sentral, 2A,

Jalan Stesen Sentral 2,

50470 Kuala Lumpur.

By accessing and using this website, you agree to comply with and be bound by the following terms and conditions:

  1. Content: The content on this website is for informational purposes only and may change without notice.

  2. Use of Information: You may use the information on this website for personal, non-commercial purposes only.

  3. Intellectual Property: All content on this website is protected by copyright and intellectual property laws.

  4. Third-Party Links: We are not responsible for the content of any linked third-party websites.

  5. Privacy: Your use of this website is also governed by our Privacy Policy.

  6. Disclaimer: This website is provided "as is" without any warranties.

  7. Limitation of Liability: We are not liable for any damages arising from your use of this website.

  8. Governing Law: These terms are governed by the laws of Malaysia.

©2023 CIPAA ADVISORS (Registered Trademark)

Proudly curated and managed by

Allix Holdings Sdn. Bhd.

bottom of page